A capacitor bank adds fixed blocks of reactive power. A static var generator (SVG) produces exactly the reactive current the load needs at that moment, in either direction. A hybrid system uses capacitor steps for the bulk and an SVG for the balance. This guide explains how to choose between them for a low-voltage (LV) installation at 380–480 V, using the load data you already have or can measure.
Our short answer, from the compensation panels we build: on EV charging and solar sites, an SVG is now the usual choice. Where capacitor steps alone are not enough, a hybrid works well: capacitor steps carry the steady demand and the SVG trims the rest. A plain capacitor bank still suits steady motor loads. In every case the decision depends on the equipment on site and the utility’s requirements, and the rest of this guide shows how to check both.
It does not cover medium-voltage SVC or STATCOM installations at substations. Those are engineered by the utility or a specialist with network studies.
The options at a glance
Most LV projects choose between four arrangements. The table compares them on the points that usually decide the choice.
| Arrangement | How output is adjusted | Output direction | Typical response | Usually suits |
|---|---|---|---|---|
| Capacitor bank, contactor-switched | Fixed steps switched in and out by contactors | Supplies reactive power to inductive loads only | Seconds to minutes between steps | Steady or slowly changing motor and building loads |
| Capacitor bank, thyristor-switched | Fixed steps switched by thyristors at a zero-voltage point | Supplies reactive power to inductive loads only | Within about one cycle; re-switching limited by discharge | Loads that change every few seconds: welders, cranes, presses |
| SVG | Power-electronic converter, continuously variable | Supplies or absorbs reactive power | Typically within one cycle | Fast or unpredictable loads, leading power factor, phase imbalance |
| Hybrid (capacitor steps + SVG) | Capacitor steps for the bulk, SVG fills the gaps | Mostly inductive correction; the SVG adds a limited range in either direction | Steps as above; SVG within one cycle | Large loads that also need fine or fast correction |
The terms used in quotations are not always consistent. Check which of these a supplier means:
- SVG and STATCOM describe the same type of converter. Suppliers of LV equipment usually say SVG; utilities usually say STATCOM.
- SVC normally means thyristor-controlled reactors and switched capacitors, mostly at medium and high voltage. It is not the same as an SVG.
- Hybrid in an LV quotation usually means capacitor steps working with an SVG. Some suppliers also use “hybrid switch” for a composite switch, which is a switching device inside a capacitor bank, not an SVG.
Tap or click the diagram to open it full size.Figure 1. What each arrangement can deliver. A capacitor bank can only add steps of capacitive output. An SVG can move continuously in both directions within its rating.
The difference in practice is resolution. In a typical LV capacitor bank the smallest step is around 10 kvar, so the power factor can only get as close to the target as one step allows. An SVG adjusts its output in increments of about 0.1 kvar, which is effectively continuous. On the sites we supply, an SVG holds the power factor at about 0.99, and it can do so whether the load is drawing inductive or capacitive reactive power.
Start with the load, not the equipment
The right choice depends on how the load behaves, so collect the data first. At the main incomer, log at least one full working week with a power quality analyser, at intervals of one second or faster if the load changes quickly. Record:
- Active power (kW), reactive power (kvar) and displacement power factor, phase by phase
- Whether the power factor is ever leading, and when (nights, weekends, light load)
- Current harmonic distortion (THDi) and the individual 5th, 7th, 11th and 13th harmonics
- The minimum load as well as the maximum
- Operation on generator, and UPS bypass events, if they occur
For a new building there is no load to measure. Use the load schedule, the equipment types and a similar existing site as the reference, and leave space in the panel for later changes. Our guide on how to size an APFC capacitor bank covers the kvar calculation.
Five questions that decide the choice
Tap or click the diagram to open it full size.Figure 2. A simplified decision path. Real projects often meet more than one condition; the flowchart shows which condition usually decides.
1. How fast does the reactive demand change?
A contactor-switched bank cannot switch the same step again until its capacitors have discharged. IEC capacitor standards allow up to three minutes for the voltage to fall to 75 V, and controllers add their own delay between steps. The CHINT NWK1-G controller, for example, has an adjustable switching delay of 5 to 180 seconds.
If the demand changes every few seconds, as with spot welders, cranes or presses, a contactor bank lags behind. In our experience the same applies to welding machines, EV chargers and loads on variable-speed drives: their reactive demand comes in bursts that are over before a capacitor step can be switched. The power factor averaged over the billing period may still be acceptable, but voltage dips and flicker at the switchboard will not improve. Thyristor switching or an SVG is the usual answer.
2. Does the power factor ever go leading?
A capacitor bank can only supply reactive power to inductive loads. It cannot correct a leading power factor; it makes it worse. Leading power factor is more common than many buyers expect:
- IT power supplies with active power factor correction draw slightly leading current. TCI reports typical values of 0.95 to 0.98 leading.
- Long cable runs at light load, for example at night or at weekends, can leave the system with a net capacitive load once the inductive loads are off.
- Many electronic loads draw reactive current even in standby, so the power factor at very light load can be poor even when it is good at full load.
If the log shows leading periods, choose an SVG or a hybrid with an SVG large enough to absorb that leading demand. Check also that the capacitor controller disconnects steps before the system goes leading.
3. How much harmonic current is there?
Harmonics affect capacitors and SVGs differently. A capacitor bank can resonate with the network at a harmonic frequency, so where drives, rectifiers or UPS units are significant it needs detuning reactors. Our article on when an APFC panel needs detuned reactors explains the selection.
An SVG does not resonate in the same way, and some models can also filter a limited amount of harmonic current. Filtering uses part of the converter’s rating, so a unit that filters harmonics has less capacity left for reactive power. If harmonic filtering is the main requirement, compare an active harmonic filter as well.
4. Are the phases unbalanced?
A conventional three-phase capacitor bank switches all three phases together. If single-phase loads make the phases unequal, it cannot correct one phase more than another. Split-phase capacitor banks with phase-by-phase switching help with moderate imbalance. An SVG with unbalance compensation can correct each phase independently; confirm that the selected model has this function, because not all do.
5. Does the system run on a generator or UPS bypass?
Generators tolerate only a limited amount of leading reactive power. Capacitor banks are usually blocked during generator operation for this reason, as explained in our article on why capacitor banks are switched off on generator power. Where the load itself is capacitive, as in a data centre during UPS bypass, an SVG that can absorb reactive power is one way to keep the generator within its limits. The generator supplier should confirm that arrangement.
Response time: what limits each option
Tap or click the diagram to open it full size.Figure 3. Typical response ranges from manufacturer data. Actual times depend on the model, its settings and the capacitor discharge arrangement.
- Contactor switching. The limit is the controller delay and the capacitor discharge time, not the contactor itself. A step switched out cannot be switched back in until its voltage is low enough.
- Thyristor switching. The thyristor closes at the right point on the voltage wave, within about one cycle. TDK’s TSM-LC-N datasheet gives a switching time of about 5 ms and states that the re-switching time depends on the detuning factor and the discharge resistor. A thyristor does not isolate the capacitor when it is off, so the step still needs a fuse-switch or isolator for safe maintenance.
- SVG. The converter adjusts its output within milliseconds. Published full-response figures are typically under 20 ms; for example, Hitachi Energy’s PQCR states less than 20 ms and TDK’s PQvar less than 15 ms.
How a hybrid system is put together

Figure 4. An electronic compensation cabinet built by Zejiefu, fitted with wall-mounted power-electronic modules of the type used for SVG and active filtering.
A hybrid system is two compensators sharing one job. Three design points decide whether it works well.
Sizing the two parts
The capacitor steps carry the steady part of the demand. The SVG covers the gaps between steps and the fast changes. An SVG uses more power to run than a capacitor bank, so we design hybrids to let the SVG work as little as possible: the capacitors take the bulk, and the SVG only trims. As a starting point, the SVG should be rated at least half of the largest capacitor step, so that its output can cover the gap between any two steps. A published design study of a capacitor and STATCOM hybrid reaches the same half-step rule. Add more SVG capacity if the log shows fast swings, leading periods or imbalance that the SVG must handle alone.
Measurement and control
The two parts must not work against each other. In our projects, two arrangements have worked well:
- Separate controllers, with the SVG’s CT upstream. The SVG’s CT sits upstream, where it measures the loads, the capacitor bank and the SVG together. The capacitor controller’s CT sits after the SVG connection, so it measures the loads and the capacitors but not the SVG. The capacitor controller then switches steps as usual, and the SVG corrects whatever the steps leave. If the CTs are placed the other way round, the SVG takes the whole load and the capacitor steps stay off. One SVG manufacturer’s project case sets out the same rule.
- The SVG controls the capacitor switching. The SVG measures at the incomer and switches the capacitor steps itself, then uses its own output to fill the gaps. With one controller in charge, the two parts cannot work against each other. TDK, for example, describes a hybrid system in which one controller coordinates the capacitor steps and the SVG.
Tap or click the diagram to open it full size.Figure 5. Measurement points in a hybrid system with separate controllers: the SVG’s CT upstream, the capacitor controller’s CT after the SVG connection. Follow the CT positions on the supplier’s approved drawing.
Either way, the drawings should show every CT, which controller it feeds and what current it measures. Our guide to reading a capacitor bank wiring diagram explains how to check CT positions.
The capacitor part still needs detuning
An SVG in the same switchboard does not stop the capacitor steps from resonating with harmonics. If the site needs detuned capacitors without an SVG, it still needs them with one. In Saudi Arabia the network frequency is 60 Hz, so the same reactor percentage gives a different tuning frequency: a 7% reactor tunes to about 189 Hz at 50 Hz but about 227 Hz at 60 Hz. Confirm that reactors and capacitors are specified for 60 Hz.
Typical applications
| Site or load | What the load usually does | Usual starting point |
|---|---|---|
| Factory with motors, pumps and compressors | Inductive, changes over minutes or hours | Contactor-switched bank, detuned if drives are significant |
| Welding, cranes, presses, stamping | Inductive, changes within seconds | Thyristor-switched bank, SVG or hybrid |
| Commercial building | Inductive by day, possibly leading at night | Contactor bank with small steps; check the night-time power factor |
| Data centre or building with large UPS | Close to unity or leading; UPS bypass events | SVG or hybrid; check generator limits |
| EV fast-charging site | Close to unity at high output; uncertain at light load and standby | SVG or hybrid, which is what we usually supply now (see below) |
| Site with solar PV | Solar covers part of the active power; reactive demand still comes from the grid | SVG or hybrid, or reactive power from the inverters (see below) |
| Long cable network at light load | Net capacitive at light load | SVG; a capacitor bank cannot help |
EV fast-charging sites
Whether a charging site needs an SVG depends on the chargers and how the site is used:
- At full output, modern DC chargers operate close to unity power factor. ABB states a power factor above 0.98 at full power for its Terra 124/184 chargers, and Kempower states 0.92 at full load for its C500 power unit. In Idaho National Laboratory testing of a 350 kW charger, the power factor was above 0.91 whenever the AC input exceeded 50 kW.
- At light load and in standby, the picture is less clear. The same INL test measured about 280 var drawn in standby and published no power factor data below 50 kW. A site with many chargers that are often idle or lightly loaded can show a poor power factor even though each charger is good at full output.
- Saudi requirements also expect reactive capability from the chargers. The SEC technical standard for EV charging systems requires chargers above 22 kW to provide reactive power control and assesses the power factor at the connection point.
Claims that fast chargers typically run at 0.6–0.8 power factor should be checked against the charger datasheet. They do not match the published data above for modern DC chargers at high output. In the charging projects we supply, an SVG is now the usual choice. Charger demand changes quickly as vehicles connect and finish, sites can swing between inductive and capacitive at light load, and an SVG follows both. The size of the SVG should still rest on the charger data and, for an existing site, on measurements.
Sites with solar PV
Solar sites are the other place where we now usually fit an SVG. By default, solar inverters supply only active power. When they cover part of the load, the site draws less active power from the grid but the same reactive power, so the power factor at the meter falls. Schneider Electric explains the effect in its Electrical Installation Guide, and describes a small industrial building where the power factor dropped from an average of 0.96 to 0.8 after solar was added, below the 0.93 required by the supplier (Schneider Electric blog).
Because solar output changes with the sun and the clouds, the reactive share at the meter changes all day. An SVG follows it continuously. On some sites the inverters can be set to supply part of the reactive power; check that option with the inverter supplier first.
Cost, losses and life in hot climates
- Initial cost. For the same nominal kvar, an SVG still costs more than a contactor-switched capacitor bank, although the price of Chinese-made SVGs has come down a lot in recent years. A hybrid sits between the two, depending on how much of the duty the SVG carries. Set the cost against the utility’s charges: in Saudi Arabia, large customers pay for reactive energy above a set share of their active energy (see the table below). Where poor power factor is being charged every month, the extra cost of an SVG is usually well worth it. Compare quotations on the same basis; our article on comparing APFC panel quotations lists the points to check.
- Losses. An SVG has converter losses of a few per cent of its rating, which is why a hybrid should let it work as little as possible. A thyristor-switched step also loses more than a contactor-switched one; TDK gives about 2 W per ampere for its thyristor module.
- Ambient temperature. Check the rated ambient for both options against the room or kiosk temperature. Schneider’s VarSet automatic capacitor banks, for example, are rated up to 45 °C. Schneider’s AccuSine EVC+ SVG runs without derating up to 50 °C and derates by 2% per °C above that. In Gulf electrical rooms without reliable cooling, either can be outside its rating. In our experience both fail quickly in hot rooms, so controlling the temperature on site matters as much as the choice between them. Our article on panel selection for hot and dusty sites covers ventilation and dust.
- Maintenance and life. Capacitors age and need periodic current checks, as described in our capacitor bank maintenance checklist. Power-electronic equipment has its own wear parts: ABB’s manual for its PQF active filters, which use a similar converter, gives a fan life of about 35,000 hours and DC capacitor life of eight to ten years. Ask the SVG supplier for its replacement intervals.
Saudi Arabia and UAE: what to check
| Item | Requirement found | Why it matters for the choice |
|---|---|---|
| Saudi Arabian Distribution Code (Issue 03, Rev 02, 2018), DPC2.4 | Power factor of at least 0.85 lagging at the connection point; users must not present a leading power factor without agreement. Larger industrial, government and commercial users (above 1 MVA) move to 0.90 and then 0.95 under a transition schedule. | Over-correction to a leading power factor is not acceptable. A capacitor bank must disconnect steps at light load, or an SVG must absorb the leading demand. |
| SEC tariff schedule | For customers above 1 MVA, reactive energy above 48.4% of active energy in a month is charged, equivalent to a 0.90 power factor. | The billing period average matters for charges; check the current threshold with SEC. |
| SEC standard for EV charging systems | Chargers above 22 kW must provide reactive power control; power factor assessed at the connection point. | Use the chargers’ own capability before adding compensation. |
| ADDC (Abu Dhabi) | Industrial consumers to maintain a power factor between 0.9 and 1.0. | Upper limit of 1.0 means a leading power factor is outside the range. |
These documents are revised from time to time, and some of the versions above are several years old. Confirm the requirement that applies to your connection with SEC, DEWA, ADDC or the relevant distribution company before finalising the design.
What to send with your enquiry
There is no single right answer: we recommend a capacitor bank, an SVG or a hybrid system based on the equipment on site and what the grid requires. To do that, a supplier needs to understand the load. Send as much of the following as you have:
- Single-line diagram with transformer rating, incomer rating and the proposed CT position
- Power quality log at the incomer (kW, kvar, power factor and THDi, phase by phase), or the load schedule for a new project
- Main load types: motors and drives, welders, UPS, chargers, lighting
- Target power factor and the utility’s requirement
- Generator and UPS arrangements, and whether compensation must run on generator
- Room temperature, cooling and available space